I have set the rules as per cost component structure and now when i am calculating WIP then i am getting three errors one of which states
No WIP at target costs could be calculated
Message no. KJ276
One of the reason mentioned in this error is that confirmation may have been done at header level. I created a planned order for PCC and did its operation wise confirmation is MFBF with post with correction button but still same the error persists.